Sl. | Project | Description |
1 | Airport Project, with Zahran Operation and Maintenance | - Primary Injection Testing of LV Breakers.
- Secondary Injection Testing of MV Protective relays.
- Infra-red thermo graphic inspection of RMUs, LV Breakers, MV/LV bus-bars
- Calibration of Electrical Analog Panel Meters.
|
2 | KKMC, Hafar Al Batin Testing and commissioning of new sub-station. | - Step-up Transformer 13.8 / 33 kV, 40 MVA.
- MV Switchgear, along with SF6 breakers.
- Auxiliary transformer 1000 kVA, 630 kVA
- Protection relays.
- Contact resistance.
- Primary injection test of breakers
|
3 | Petro Rabigh | Testing & Commissioning of GUTOR (Sweden) UPS Capacity 50kVA |
4 | Le Meridien Al Hada (Taif) | - Infra-red Thermo graphic inspection of all electrical distribution panels.
- Installation of Fire Fighting Water pipe line along with Fire Hose Cabinets and 8” dia Pressure Reducing Valve (PRV).
- Installation of grounding system for central PABX
|
5 | National Water Company | - Replaced a Ring Main Unit (RMU) at Sewage Treatment Plant Al Ruwais.
- Replaced Oil in 2500 kVA distribution Transformer.
|
6 | Tabuk, Al Wedjh, Hail and Al Ula airports. | - Testing of LV main breakers of all distribution sub-stations.
- Transformer Turn Ratio Testing of all distribution transformers
|